Tanjung Priok Access Toll Road Construction Reaches 98 Percent
Reported by Budhi Firmansyah Surapati | Translated by Rizky Mawardi
The construction of Tanjung Priok Access Toll
road has reached 98 percent. It is predicted the finalizing of section E2 is on target and can be operated in March.The construction has been connected, it's already 98 percent. We're optimistic to operate in March
Head Division of Implementation II for Balai Besar National Road IV Gen. Dir. of Bina Marga, Ministry of Public Works and Public Housing, Bambang Nurhadi, said the project leaves asphalting and railing.
"The construction has been connected, it's already 98 percent. We're optimistic to operate in March," he said, Tuesday (1/10).
Council Recommends Traffic Jam Solution in N. JakartaHe added that the other four packages have been completed, as well as the four ramp off in Pasar Waru, Makam Mbah Priok, North Jakarta Mayor Office and Semper.
"There are six ramp on in KBN, Semper, Bogasari, Jalan Dobo, RS Koja and Kebon Bawang," he added.
Tanjung Priok Access Toll construction along 16.67 km was divided into five packages.
There are East 1 Section (E1) Rorotan-Cilincing along 3.4 km, East 2 Cilincing-Jampea 2.74 km, East 2-A Cilincing Jampea 1.92 km, North-South Link (NS Link) Yos Sudarso-Simpang Jampea 2.24 km, and North-South Direct Ramp by 1.1 km.